Mar 9, 2013

New Load-shedding schedule effective from March 11 (Falgun 28).

Nepal Electricity Authority has announced the new load-shedding schedule to be reduced by 2 hours per day.  Issuing a notice today, NEA informed media of power cut hours to be made 10 hours from 12 hours per day. Citing the SLC examination, NEA decreased the load-shedding hours to alleviate the worst condition for students which is possible due to additional electricity from India, significant amount of water level in Kulekhani resorvoir and maintenance of Kali Gandaki A Hydro.

Here is the new load shedding schedule to be effective from March 11 (Falgun 29) but published on March 9. Click to download or larger picture.